Skip to main content
LOW997Industrial Systems

Commercial & Industrial Buildings

Commercial Solar ESS

Rooftop solar plus battery storage behind the meter — one converter, demand-charge reduction, and backup for the circuits that actually matter.

  • One 100 kW converter replaces PV inverter, battery inverter and transfer switch
  • Dual MPPT inputs, 200–1 000 V DC each
  • Volt-var, frequency-watt and ride-through for grid connection approval
  • 10 ms grid-forming backup on the circuits that matter
Commercial building with rooftop solar array, outdoor battery cabinet and wall-mounted hybrid power conversion system
Peak conversion efficiency
98.6 %
PV inputs per converter
2 MPPT
Power factor range to −0.9
+0.9
Outdoor enclosure rating
IP66

Problems this solves

Stated plainly, because a solution that does not name the problem it removes is a product brochure.

  • Midday export earns the lowest price of the day

    A commercial array without storage exports during the hours when wholesale and feed-in values are at their lowest, then buys power back at the evening peak. The array is doing the work and the site is capturing almost none of the value, which is why so many rooftops fail their payback model.

  • Demand charges are set by a fifteen-minute window

    A single coincident spike — chillers, lifts and a charger starting together — sets the billing demand for the whole month. It is a capacity charge, not an energy charge, and no amount of generation during the rest of the month buys it back.

  • A separate inverter, transfer switch and controls cabinet

    Conventional designs split the PV inverter, the battery inverter, the static transfer switch and the site controller across four boxes from three suppliers. Every interface is a fault path, every firmware update is a compatibility question, and commissioning takes weeks rather than days.

  • Grid connection approval fails on power quality

    Network operators increasingly require volt-var response, frequency-watt behaviour and ride-through before they will permit a generating plant in parallel with the LV network. Equipment without those functions delays the whole project, and retrofitting them is not a firmware patch.

Our engineering approach

  1. 1Model the site's half-hourly consumption against its generation profile before sizing anything, and separate the savings into self-consumption, demand-charge reduction and backup value so the payback case is auditable line by line.
  2. 2Use one bidirectional converter with dual MPPT inputs so the array and the battery share a single grid interface, removing an inverter, a cabinet and a set of drawings from the balance of plant.
  3. 3Configure volt-var, volt-watt and frequency-watt characteristics to the published grid-code curve of the local network operator, and hand over the settings record and type test certificates for the permit application.
  4. 4Arm grid-forming island mode on the backed-up circuits so the same hardware that optimises the tariff also carries the site through an outage in 10 ms.
  5. 5Commission against a written site acceptance test that the operator's engineer and the insurer can both sign, with register maps issued to the building management system.

Solution overview

Where the money actually comes from

A commercial storage project is usually justified with a single number and then audited against three. We separate them from the start, because they have different drivers, different risks and different sensitivities to tariff change.

Value stream Driver Sensitivity
Self-consumption Solar generation vs site load shape Falls if the tariff flattens
Demand-charge reduction Peak shaving across the billing window Falls if the site load profile changes
Backup and resilience Cost of downtime on critical circuits Rises with outage frequency

A site with a flat load and a low demand charge is a self-consumption project. A site with chillers, lifts and a spiky profile is a demand-charge project. The same hardware serves both, but the dispatch strategy and the battery duration are different, and quoting the wrong one is the fastest way to a project that never pays back.

One converter, fewer interfaces

The HP-100 takes the PV array on two independent MPPT inputs and the battery string on a 200–1 000 V DC input, behind a single 400 V AC grid interface.

That removes the PV inverter, the separate battery inverter and the static transfer switch. It also removes the three communication links between them, which is where most of the commissioning time on a conventional design is actually spent.

Passing the grid connection review

Network operators ask for functions, not for products. The HP-100 implements volt-var, volt-watt, frequency-watt and configurable ride-through, and ships with the type test certificates, the settings record and the EN 50549-1 declaration.

The configuration is set in the factory against the target grid code, so the on-site engineer confirms rather than writes the characteristic curve.

Backup as a by-product

Arming island mode on the backed-up circuits adds resilience without adding hardware. The converter forms its own 400 V reference and transfers in 10 ms, which covers chillers, servers, access control and lighting through a short outage — and it is rated 110 % continuous with 150 % for 10 s so motor loads start without an oversized unit.

Delivery

Storage modules carry a 28-day lead time, converters 42 days. Site acceptance test procedures, register maps and the compliance pack are issued with the quotation. Commissioning support is available to the installing contractor at no additional cost.

Every line below is a catalogue item with a published specification and a declared certification set. Nothing here is a configuration that exists only inside a quotation.

  • HP-100 hybrid power conversion system in an IP66 outdoor enclosure with separate AC and DC cable entries

    Energy Storage & Power Conversion

    HP-100 Hybrid Power Conversion System

    Model HP-100

    100 kW bidirectional converter with dual MPPT inputs and grid-forming backup transfer in 10 ms, rated IP66 for outdoor installation.

    Rated AC power
    100 kW, four-quadrant bidirectional
    AC connection
    400 V AC three-phase + N + PE, 50 / 60 Hz
    • UL 1741 SB
    • IEC 62477-1
    • IEC 62109-1 / -2
    View specifications
  • BR-48100 rack-mounted LiFePO4 battery module with front terminal studs and RJ45 communication ports

    Energy Storage & Power Conversion

    BR-48100 Rack-Mounted LiFePO4 Battery Module

    Model BR-48100

    51.2 V / 100 Ah lithium iron phosphate module with an integrated BMS and CAN telemetry, sized for 19-inch cabinets in telecom and commercial sites.

    Cell chemistry
    LiFePO4 (LFP), prismatic
    Nominal voltage
    51.2 V DC
    • UL 1973
    • IEC 62619
    • UN 38.3
    View specifications
  • Telecom base station cabinet with rack-mounted lithium battery modules and a wall-mounted hybrid converter

    Telecom & Data Infrastructure

    Telecom Backup Power

    48 V DC lithium backup for base stations and edge cabinets — sized per site, shipped as a shelf, monitored over the same CAN bus the network already uses.

    Cycles to 80 % capacity
    ≥ 6 000
    Transfer to island mode
    10 ms

    4 documented problems2 recommended product lines

    Read the solution